Lesson 8 of 9 · about 16 minutes
Costs and timelines: Vogtle and the SMR bet
You'll be able to
- State Vogtle 3 and 4's original and final cost and schedule with sources
- Explain the main causes of nuclear cost overruns identified by researchers
- Calculate cost per kilowatt and compare projects fairly
- Summarize the strongest arguments for and against small modular reactors on cost
Safety used to be the main argument against nuclear power in the United States. Today it is cost. Reactors are cheap to run once built: fuel is a small share of the bill and they run more than 90 percent of the time. Building them is the problem. The last two finished in the U.S. took about 15 years from the start of construction in 2009 to full operation and more than doubled their budget.
Vogtle 3 and 4
Plant Vogtle near Waynesboro, Georgia, already had two reactors from the 1980s. In 2009 Georgia Power and three co-owners began building two Westinghouse AP1000s, the first new U.S. reactor construction in about 30 years. The design was supposed to fix the industry's old problems: standardized, simplified, with passive safety and modules built in factories.
| Original plan | What happened | |
|---|---|---|
| Total cost | About $14 billion | About $31 billion for the owners (AP calculation), near $35 billion counting $3.7 billion Westinghouse paid the owners |
| Unit 3 in service | 2016 | July 2023 |
| Unit 4 in service | 2017 | April 2024 |
| Capacity | About 1,100 MWe each | About 1,114 MWe each; with four units Vogtle is the largest U.S. nuclear plant, at nearly 5 GW |
| Contractor | Westinghouse | Westinghouse filed for bankruptcy in 2017 |
Georgia Power customers pay through their bills. AP reported that the final rate increase added about $8.95 a month to a typical residential bill, on top of $5.42 a month added when Unit 3 started. Southern Company, Georgia Power's parent, estimated a shareholder loss of about $3 billion. In South Carolina, the sister project at V.C. Summer, two more AP1000s, was abandoned in 2017 after about $9 billion was spent. The NRC terminated its licenses in 2019. Customers there are still paying for reactors that will never run.
Example: cost per kilowatt
Vogtle 3 and 4: about 2 × 1,114 = 2,228 MWe, call it 2,230 MW = 2,230,000 kW.
$35,000,000,000 ÷ 2,230,000 kW ≈ $15,700 per kW. Using the $31 billion owner figure: ≈ $13,900 per kW.
The original $14 billion for roughly the same capacity: ≈ $6,300 per kW.
Compare the NuScale project cancelled in 2023: $9.3 billion ÷ 462,000 kW ≈ $20,100 per kW, the figure IEEFA reported. And OPG's first BWRX-300 at Darlington: US$5.6 billion ÷ 300,000 kW ≈ $18,700 per kW (that figure includes shared site costs for later units, so it overstates the per-unit cost somewhat).
Always say which cost you are using, whether it includes financing, and what year's dollars it is in.
Why nuclear projects overrun
The best-known study of this is "Sources of Cost Overrun in Nuclear Power Plant Construction Call for a New Approach to Engineering Design" by Jessika Trancik, Jacopo Buongiorno and colleagues at MIT, published in Joule in 2020. Looking at U.S. plants over decades, they found the largest driver of rising costs was indirect or "soft" costs: engineering, planning, supervision and the costs of crews waiting during delays. Safety regulations added cost, they found, but were one factor among several. And their most surprising finding was that later plants of an existing design often cost more, not less, than the first, the opposite of the learning curve industry expected.
Vogtle shows most of the usual problems:
- Design not finished before construction: work began while parts of the design were still changing, which forced rework.
- Supply chain atrophy: after decades without new U.S. reactors, few suppliers had current nuclear quality experience. Modules built off site arrived with defects.
- Workforce: crews had to learn nuclear-grade construction on the job; at the peak, thousands of workers were on site.
- Contract structure: fixed-price deals pushed risk onto Westinghouse until it went bankrupt, then risk came back to the utility and its customers.
- Financing: every year of delay adds interest. On a $30 billion project at 6 percent, a year of delay can add well over a billion dollars in interest alone.
Pro-nuclear analysts also point to regulation. They argue that the NRC's process, frequent rule changes during construction and the cost of documenting every safety-grade component add cost without matching safety benefit. Anti-nuclear and consumer groups answer that the overruns at Vogtle were mostly construction management failures, and that the problem is the technology's complexity. Both camps agree first-of-a-kind projects are where the money gets lost.
The SMR bet
Small modular reactors are the industry's answer to Vogtle. The arguments on each side are worth laying out in their strongest form.
| What SMR advocates argue | What skeptics argue |
|---|---|
| Smaller projects mean less money at risk per project; a utility can add capacity in 300 MW steps instead of betting billions on one unit | Reactors historically got cheaper per kW by getting bigger. Smaller units lose economies of scale in containment, staff and security |
| Factory production brings learning: each unit cheaper than the last | Factory savings need a steady order book of dozens of units; there is no such order book yet, and the MIT study found little historic learning |
| Passive safety and smaller cores reduce the need for expensive safety systems and large emergency zones | Early SMR estimates, like NuScale's in 2023 and Darlington's, came in at $18,000 to $20,000 per kW, higher than Vogtle |
| Tech companies will pay premium prices for firm, carbon-free power, which absorbs first-of-a-kind costs | If tech buyers pay the premium, fine; if costs land on ordinary utility customers, they carry the risk |
| Sites at retired coal plants reuse grid connections, water rights and trained workers | Advanced designs need HALEU, which is scarce, and many have never operated at commercial scale |
Groups that make the skeptical case include the Institute for Energy Economics and Financial Analysis (IEEFA), which tracked the NuScale cost increases, and the Union of Concerned Scientists. The advocacy case comes from the Nuclear Energy Institute, think tanks such as the Breakthrough Institute, and DOE's own "Pathways to Commercial Liftoff" report, which argues that a committed order book of five to ten deployments of at least one reactor design is what it would take to drive costs down, and sets a goal of on-time, on-budget delivery within plus or minus 20 percent.
Where does the evidence point? Clearly on one thing: first-of-a-kind reactors in North America have been expensive, and no SMR has yet shown the cost declines its backers predict, because none has been built in series. Whether the learning shows up is the test of the next decade. Executive Order 14302 (May 2025) directed DOE to help get 10 new large reactors with complete designs under construction by 2030 and 5 GW of uprates at existing plants, a signal that Washington is betting on both large and small reactors.
Who carries the risk
For residents and ratepayers, the money question is usually more important than the technology question. Ask who pays if it runs over.
- Regulated utility customers: in states that allow it, utilities can charge customers during construction (construction work in progress, or CWIP), as Georgia did. That cuts financing costs but shifts risk to ratepayers.
- Public power: TVA, municipal utilities and co-ops pass costs to their members. The Utah cities in the NuScale project were exposed until they withdrew.
- Tech company buyers: a fixed-price PPA puts some risk on the buyer, but the details matter: who pays if the plant is late?
- Taxpayers: DOE loans, grants (like the up to $400 million in cost-shared funding DOE selected TVA for at Clinch River) and tax credits for nuclear production and investment spread cost to the public.
- Investors: merchant developers and venture-backed startups carry risk directly, which is why their schedules depend on raising capital.
Common mix-ups
- Claim: Nuclear power is expensive because uranium is expensive. What the evidence shows: Fuel is a small share of nuclear's cost. Construction and financing dominate.
- Claim: Regulation alone explains the cost overruns. What the evidence shows: The MIT study found soft costs and construction problems were the largest drivers, with regulation one contributing factor.
- Claim: SMRs are proven to be cheaper. What the evidence shows: Not yet. Published first-unit estimates have been high per kilowatt. Cheaper later units are a projection.
Reporting angle
At your state utility commission, look for dockets where a utility asks to include a reactor in its resource plan, to recover pre-construction costs, or to sign a PPA with a reactor developer. Read the cost estimate, the contingency percentage, and the cost-overrun terms. Ask for cost per kW in the developer's own numbers and in what year's dollars. Compare against Vogtle and Darlington. For a public power utility, ask whether members can withdraw, at what cost, and by what date, the exact question that ended the NuScale project.
Research angle
- EIA Today in Energy on Vogtle Unit 4 entering commercial operation.
- WABE and AP report on the Georgia regulators' Vogtle cost deal.
- MIT News on the causes of nuclear construction cost overruns.
- IEEFA analysis of NuScale cost estimates.
- DOE Pathways to Commercial Liftoff report on advanced nuclear.
- NRC list of combined license holders, including terminated licenses.
Check yourself
1. What was the original estimated cost of Vogtle Units 3 and 4?
The project was first estimated at about $14 billion. The AP calculated about $31 billion in owner costs, near $35 billion with Westinghouse's $3.7 billion payment.
2. When did Vogtle Unit 4 enter commercial operation?
EIA reported Unit 4 entered commercial operation at the end of April 2024, completing an 11-year expansion. The original target was 2017.
3. The 2020 MIT study in Joule found the largest driver of rising U.S. nuclear construction costs was what?
The study by Trancik, Buongiorno and colleagues found soft costs, such as engineering, planning and labor supervision during delays, drove most of the increase.
4. Why did the NuScale and UAMPS Carbon Free Power Project end in 2023?
The estimated cost rose from $5.3 to $9.3 billion and the target price from $58 to $89 per MWh in early 2023; members dropped out and it was cancelled in November 2023.
5. What does 'first-of-a-kind' (FOAK) cost refer to?
First units carry design completion, supply chain setup and learning costs. Advocates expect later 'nth-of-a-kind' units to be cheaper.
6. Vogtle 3 and 4 total about 2,228 MWe. At $35 billion, what is the rough cost per kilowatt?
$35,000,000,000 ÷ 2,228,000 kW ≈ $15,700 per kW.
Terms in this lesson
- Overnight cost
- The cost to build a plant as if it were built instantly, excluding interest during construction.
- Cost per kilowatt ($/kW)
- Total construction cost divided by electric capacity; the standard way to compare plants of different sizes.
- FOAK and NOAK
- First-of-a-kind and nth-of-a-kind: the first units of a design versus later ones built after learning.
- Construction work in progress (CWIP)
- A rate practice that lets a utility charge customers for a plant while it is still being built.
- Levelized cost
- Lifetime cost of a plant divided by lifetime energy produced, expressed in dollars per MWh.
Sources
- WABE/AP: Regulators approve deal to pay for Georgia Power's new nuclear reactors checked 2026-10
- EIA Today in Energy: Vogtle Unit 4 enters commercial operation checked 2026-10
- MIT News: Study identifies reasons for soaring nuclear plant cost overruns (2020) checked 2026-10
- IEEFA: Eye-popping new cost estimates released for NuScale SMR (2023) checked 2026-10
- Power Magazine: NuScale's 77-MWe SMR clears NRC review (CFPP cancellation) checked 2026-10
- DOE Pathways to Commercial Liftoff: Advanced Nuclear checked 2026-10
- BWRX-300 (Darlington cost forecast) checked 2026-10